General Overview
Overview by District
Category | Development Phase |
Development Area (thousand m²) |
Project Cost (billion KRW) |
Project Duration | Project Executor | Introduced Function |
Progress Rate | Remarks | ||
---|---|---|---|---|---|---|---|---|---|---|
Total | 19,559 (23,710) |
81,573 | ||||||||
Completed(6) | 1 | New Port Hinterland (North) | 1-1 | 2,442 (3,085) |
5,476 | '00~'12 | Ministry of Oceans and Fisheries, Busan New Port Co., Busan Urban Corporation, Busan Port Authority | International Business, Logistics | Completion('12.12) | Gyeongnam/Busan |
2 | Namyang District | 1-2 | 293 | 575 | '03~'09 | LH | Advanced Production | Completion('09.11) | Gyeongnam | |
3 | Nammun District | 1-2 | 1,086 | 3,478 | '06~'14 | Gyeongnam Development Corporation | High-tech Industry, Residential | Completion('14.08) | Gyeongnam | |
4 | Yongwon Leisure District | 1-1 | 1,691 | 80 | '88~'91 | Yongwon Development Co., Ltd. | Leisure, Recreation | Completion(‘91.11) | Gyeongnam | |
5 | Macheon Industrial District | 1-1 | 611 | 794 | '88~'01 | Macheon Foundry Complex | Advanced Production | Completion(‘01. 1) | Gyeongnam | |
6 | Dudong District | 1-2 | 1,677 | 4,238 | '04~'19 | Busan-Jinhae Free Economic Zone Authority | Logistics, Residential | Completion('19.07) | Gyeongnam | |
In Progress(6) | 7 | Cultural District | 1-2 | 165 | 265 | '07~'15 | - (Project Executor Cancelled on April 2020) |
Restoration of Kiln Sites | Phase 1 Project Completion | Gyeongnam |
8 | Bobe Complex District | 1-2 | 802 | 2,871 | '03~'27 | Bobe Industrial Co., Ltd. | Research, Industry | Progress 27% | Gyeongnam | |
9 | Ungdong District (1) | 1-2 | 2,258 | 3,461 | '03~'22 | Former Changwon City Corporation (Project Executor Cancelled on March 2023) | Leisure, Recreation | Progress 64% | Gyeongnam | |
10 | Ungdong District (2) | 1-2 2 |
4,104 | 8,487 | '03~'27 | Ministry of Oceans and Fisheries, Busan Port Authority, Busan New Port Ungdong Development Co., Ltd. | Logistics, Distribution | Progress 74% | Gyeongnam | |
11 | New Port District | 2 | 3,015 (6,483) |
45,735 | '03~'27 | BPA and three other companies | Logistics, Distribution | Progress 94% | Gyeongnam/Busan | |
12 | Wasung District | 1-2 | 790 | 3,251 | '09~'27 | Gyeongnam New Port Co., Ltd | Industry, Logistics | Progress 20% | Gyeongnam | |
Not Started (1) | 13 | Ungcheon-Namsan District | 1-2 | 665 | 2,862 | '07~'23 | Former ULC Co., Ltd. (Project Executor Cancelled on January 2023) | Residential, Commercial | Revocation of Project Executor Designation('23.1.19.) | Gyeongnam |